Connectivity Infrastructure in Dholera Smart City
Dholera Smart City is developing world-class multi-modal connectivity to establish itself as a global logistics and manufacturing hub.
Air Connectivity
Dholera International Airport (Under Construction)
- Location: 15 km from Dholera SIR
- Area: 1,426 hectares
- Phase 1 Investment: ₹1,305 crore
- Runway: 3,200 meters (Phase 1); second 4,000-meter runway planned
- Operational Timeline: Phase 1 cargo services expected early 2026; full completion December 2025
- Capacity: 1.5 million passengers annually (Phase 1)
- Developer: Dholera International Airport Company Limited (DIACL) - AAI 51%, Gujarat Govt 33%, NICDC Trust 16%
- Significance: Global air cargo and passenger access for high-value manufacturing sectors
Existing Airports (Proximity)
- Ahmedabad International Airport: 117 km
- Vadodara Airport: 140 km
- Bhavnagar Airport: 60 km (closest operational airport for domestic travel)
Road Connectivity
Ahmedabad-Dholera Expressway (NH 751)
- Length: 109 km access-controlled corridor
- Status: 98% complete as of December 2025
- Travel Time: 45 minutes from Ahmedabad
- Full Operation: Expected May/June 2025
- Contractor: Sadbhav Engineering Ltd (Packages 1 and 2, 48.52 km)
- Significance: Reduces travel time from 2+ hours to under one hour
Delhi-Mumbai Expressway
- Distance: 120 km from Dholera
- Significance: Connects Dholera to India's premier industrial corridor
- Benefits: High-speed logistics to Delhi and Mumbai regions
Current Connectivity
- Connected to Ahmedabad through NH 751 & 47
- Internal road network: 72 km within Activation Area
Rail Connectivity
Bhavnagar-Dholera Railway Line
- Status: Final Location Survey ordered by Union Railway Minister Ashwini Vaishnaw
- Length: 65 km broad-gauge line
- Allocation: ₹466 crore for construction
- Connection: Links to Western Dedicated Freight Corridor (WDFC) at Sanand (100 km)
- Purpose: High-capacity freight corridor for industrial goods
- Timeline: Land acquisition being fast-tracked by state government
Passenger Rail
- Status: Passenger rail connectivity from Ahmedabad approved
- Proposed: Metro Rail Transit System (MRTS) to facilitate workforce movement
- Dedicated Freight Corridor (DFC): 100 km planned at Sanand
Sea Connectivity
Major Operational Ports
- Pipavav Port: 200 km - handles container and bulk cargo
- Kandla Port: 300 km - one of India's largest ports
- Mundra Port: 350 km - India's largest commercial port
Proposed Bhavnagar Port
- Distance: 60 km from Dholera
- Status: Proposed development
- Significance: Short-range maritime trade efficiency
Connectivity Map Summary
| Mode | Facility | Distance | Status |
|---|
| Air | Dholera International Airport | 15 km | Under Construction (Dec 2025 completion) |
| Ahmedabad International Airport | 117 km | Operational |
| Bhavnagar Airport | 60 km | Operational |
| Road | Ahmedabad-Dholera Expressway (NH 751) | 109 km | 98% Complete (May 2025 operation) |
| Delhi-Mumbai Expressway | 120 km | Partial Operation |
| Rail | Bhavnagar-Dholera Line | 65 km | FLS Ordered |
| Western Dedicated Freight Corridor | 100 km (Sanand) | Planned |
| Sea | Bhavnagar Port | 60 km | Proposed |
| Pipavav Port | 200 km | Operational |
| Kandla Port | 300 km | Operational |