Understanding Dholera Town Planning Schemes

The Town Planning (TP) Schemes in Dholera are the practical implementation tools that translate the master plan into actionable development. Using a unique land pooling mechanism under the Gujarat Town Planning and Urban Development Act, 1976, these schemes reorganize land parcels to build modern infrastructure without traditional government land acquisition.

Land Pooling Mechanism

Under the land pooling (reconstitution) system:

  • Land from various owners is consolidated and planned with essential utilities and roads
  • Land is redistributed back to owners as "Final Plots"
  • Authority retains 40-50% of land for "Trunk Infrastructure" (roads, utilities, public amenities)
  • Remaining land value increases significantly due to world-class infrastructure

Area Distribution by Town Planning Scheme

TP SchemeArea (km²)PercentageKey Villages Covered
TP 151.4112.17%Ambli, Kadipur, Bhadiyad, Gogla
TP 2102.3424.23%Bhadiyad, Gorasu, Otariya, Sandhida, Kadipur, Dholera, Khun, Bhim Talav, Mundi, Raha Talav
TP 366.6015.76%Sodhi, Cher, Otariya, Sangasar, Sandhida, Dholera, Mundi
TP 460.0214.21%Sandhida, Dholera, Panchi, Mundi, Mahadevpura, Bhangadh, Zankhi, Hebatpur
TP 574.7517.69%Panchi, Bavaliyari, Sodhi, Sangasar, Hebatpur
TP 667.3315.94%Zankhi, Hebatpur, Bavaliyari, Bhangadh, Mingalpur

Activation Area (TP2A and TP4)

The Activation Area, located within TP2 (West) and TP4, covers 22.5 sq. km and serves as the demonstration zone with complete "plug-and-play" infrastructure:

  • 72 km of internal roads (12m to 70m wide)
  • 100% underground utilities (power, water, telecom)
  • 135 km of water pipeline network
  • 50 MLD Water Treatment Plant
  • 20 MLD Common Effluent Treatment Plant (CETP)
  • 10 MLD Sewage Treatment Plant (STP)
  • Smart grid power distribution
  • Information and Communication Technology (ICT) infrastructure

Zoning Distribution in Activation Area

  • Industrial Use: Up to 47% (semiconductor, electronics, manufacturing)
  • Residential: Up to 28% (projected 1.2 lakh residents)
  • Commercial & Institutional: 25% (business, education, healthcare)
  • Green Spaces & Recreation: 7% (parks, riverfront development)

Key Completed Projects within TP Schemes

  • ABCD Building: Administration and Business Centre (36,000 sq. meters) in TP2 Knowledge & IT Zone
  • Water Treatment Plant: 50 MLD capacity in TP1
  • Solar Park: 5,000 MW capacity in TP6 Green Energy Zone
  • Canal Front Development: 6 km riverfront in Activation Area (TP2 & TP4)
  • Tata Semiconductor Plant: In TP2 Industrial Zone